BIM Technology

Project Type

Project Value

€150m

Features:

JVT provided the Building Information Modelling (BIM) Technology for this project which consisted of a 9,500m2 Tier 3 wholesale Data Centre with 8 No. Data Halls (Evo-Pods), Electrical Loading:8.8MW, Condenser water cooling system with minimal chiller intervention, 2 No. 1,055kW Cooling Towers, 6No. 1,583kW Cooling Towers and 8 No. Chillers with Waterside Economisers

  • Produce Mechanical Validation Report
  • Produce Electrical Validation Report
  • Localise Drawings and Prepare a Metric Set of Drawings
  • Building Information Modelling to Level 2 maturity
  • Prepare 3 REVIT full Coordination Drawings for Construction
  • Localise the Selection of Plant
  • Ensure Compliance to Local Fire and Building Regulations and Codes
  • Provide onsite REVIT Engineering Staff